Roof Notice 12/9
Roof notice 12/9 Tiles will be delivered this week and installation is expected to begin this Monday, 12/13, and last 5-7 work days per building. Tile will be installed in the same order as the …
Roof notice 12/9 Tiles will be delivered this week and installation is expected to begin this Monday, 12/13, and last 5-7 work days per building. Tile will be installed in the same order as the …
Work is expected to begin on Building #4 (659-695 Hibiscus St) Monday, 7/19. All units that utilize this driveway should anticipate delays due to work vehicles. Those units are asked to plan for temporary inconveniences. …
This notice is to inform that work is expected to begin on Building #2 (640-674 Fern St) Tomorrow, 6/29. All units that utilize the North Driveway (606-674 Fern St) should anticipate delays due to work …
This notice is to inform that construction of the building with garages in the center driveway, with addresses 678-698 Fern St, is scheduled to begin either Thursday 6/17 or Monday 6/21. As roof construction is …
This notice is to inform that the building permit has been accepted. The Contractor, DBS, will be delivering some materials to the site tomorrow, Friday June 11th. The far ends of the center and south …
Cityplace Townhouse POA Roof Replacement Notice As many of you know, the POA has procured a contractor to replace the roofs within the community. A building permit application has been submitted and construction is expected …